Calculator methods, units and limits

These tools turn your supplied measurements and specification values into a checkable record. They do not choose a product, design a slab or approve work.

Product data and arithmetic have different jobs

The quantity formula is arithmetic. Consumption, bag mass, thickness limits, substrate conditions and preparation requirements come from the exact product and the application named on its data sheet. Enter the current document reference and date with those values; no product is selected automatically.

A flooring data sheet may give different requirements for different substrates, aggregate extensions and application depths. Copying only the headline maximum thickness can miss an important condition. Example manufacturer document. Its constants are not universal calculator defaults.

Compound quantities: Quick mode

For each room or zone, multiply area in m² by depth in mm and the entered consumption in kg/m²/mm. Add the zone quantities before applying the entered percentage allowance. Divide the project total by the bag mass and round up to whole bags. Apply usable whole stock bags once to the project requirement.

Net kg = Σ(area m² × depth mm × consumption kg/m²/mm)
Total kg = net kg × (1 + allowance % / 100)
Total bags = ceil(total kg / bag kg)
Bags to buy = max(0, total bags − usable stock bags)

Hypothetical arithmetic example, not a product recommendation: 10 m² at 3 mm plus 5 m² at 6 mm, entered consumption 1.4 kg/m²/mm and 22 kg bags, gives 84 kg net. With a 10% allowance the total is 92.4 kg, or five whole bags before stock. Rounding each room separately would allocate six bags; staging and shared purchasing are different quantities.

Depths must fit the thickness limits you entered. An allowance does not fix missing measurements or make an unsuitable application acceptable. The low/high depth scenarios are hypothetical sensitivity checks, not statistical confidence intervals.

Compound quantities: Survey mode

The beta accepts one complete rectangular regular grid of x, y and base reduced level (RL), all in metres. It needs distinct coordinates, regular spacing and every grid intersection. Duplicate points, holes, missing points, irregular spacing and unsupported geometry are not filled in with guesses. Grid spacing is checked to a very small relative tolerance (10⁻⁹) to allow for how computers store decimals; points are never merged.

Target RL = z0 + gx × (x − x0) + gy × (y − y0)
Depth mm = 1000 × (target RL m − base RL m)

The target is one plane you supply. Within each rectangular cell the base is modelled by bilinear interpolation. Under that model, cell area multiplied by the mean depth at its four corners gives the depth-volume term. Multiply it by the entered consumption to obtain kg.

The corner checks apply to every point, not just an average. Negative depths and corners outside the entered minimum/maximum block the validated quantity. The model cannot reveal a hump between measurements: the grid and site observations remain your responsibility.

Setting-out levels and the sign of an error

Enter one supplied plane, its origin and gradients. A positive gradient means RL rises as that coordinate increases. Keep the benchmark (BM), drawing revision and tolerance from the specification with the record. The tool neither selects the falls nor checks drainage performance.

HPC = benchmark RL + backsight
Target staff = HPC − target RL
Staff error mm = 1000 × (observed staff − target staff)
Level error mm = 1000 × (measured RL − target RL)

HPC is the height of the plane of collimation. A larger observed staff reading means the surface is lower. A larger measured RL means it is higher. These errors have opposite signs and are labelled separately.

Arithmetic check: BM 100.500 m plus backsight 1.250 m gives HPC 101.750 m. A target RL of 100.380 m gives staff 1.370 m. Observed staff 1.380 m gives staff error +10 mm and level error −10 mm. A blank observation is missing, not zero.

A tolerance comparison only compares numbers with the value you supplied. It is not an inspection certificate, an instrument calibration check or engineering approval.

Keep a durable record

Changing an input makes an earlier result out of date. Recalculate before printing or exporting. Keep the project and drawing revision, units, exact inputs, product/specification references, calculation version, assumptions and unresolved items together.

JSON is the editable file record; an imported record must be validated and recalculated, not trusted because it contains old results. CSV is a tabular handover. Optional browser saving is inputs-only convenience on that device, not a backup. See privacy for the local-data distinction.

These are arithmetic beta tools. They have not been field-tested, and they do not assess structural suitability, safe loading dates or curing compliance. Sources explains which references support the guidance and which values remain yours to supply.

The quantity worksheet uses the supplied product consumption rate, measured area and thickness. A shared bag order pools the quantity; separately staged rooms can require more rounded-up bags.

The levels worksheet applies a supplied target plane, not an inferred design. Level and staff-reading error use opposite signs: a staff reading above its target corresponds to a surface level below its target. The supplied tolerance is checked separately.