Work from the measurements, approved drawing and product data sheet for your job. The workbench shows the arithmetic and keeps your assumptions with the result. No login needed.
Add rooms and measured depths, or import a complete regular level grid. Use your exact product rate and thickness limits, then work to one shared bag order.
Four different stages, not one countdown. Keep the prescribed curing method and the decision about loading separate from quantity arithmetic.
Field guide
These are arithmetic tools, not an engineering sign-off. Check the entered measurements and specification before using a record on site.
Placing concrete from a delivery chute
02 · See the working
Show the working, then the order.
A small example for each tool. These figures illustrate the arithmetic; they are not a recommended product or a design for your job.
Self-levelling compound · example project
Ground-floor rooms
Illustrative two-room compound order
Zone
Area × depth
Net
Kitchen
10 m² × 3 mm
42 kg
Hall
5 m² × 6 mm
42 kg
Net
at 1.4 kg/m²/mm
84 kg
Order
+10% allowance
92.4 kg
5
× 22 kg bags, one shared order 110 kg purchased, none in stock. Rounding each room separately would mean 6 bags.
All product values are illustrative inputs. For a real job, enter the current data-sheet rate, bag size, thickness limits and application for the exact product, as named on its data sheet.
Benchmark 100.500 m, backsight 1.250 m and target RL 100.380 m give a target staff reading of 1.370 m.
An observed staff reading of 1.380 m means staff error +10 mm and level error −10 mm. The surface is 10 mm low, not high. Your specification supplies the tolerance.
Four guides to the distinctions behind an order, a pour or a flooring decision. They explain the terms; your project specification still supplies the requirements.
Keep setting, curing, floor moisture testing and permission to load separate.
Levelling freshly placed concrete
03 · Pour & finish guide
Before you place the first load
Datum and measurements
Fix one datum and note where its level came from. Measure the base you will actually place material onto. Drawing depths are not a floor survey.
Logistics
Walk the route from delivery to placement. Confirm access, delivery arrangements and the placing plan with the people responsible for the job.
Specified joints
Work from the joints on the drawing or specification. If that information is missing, resolve it with the designer rather than guessing a spacing.
Prescribed curing
Have the specified protection ready before placement. Method, start conditions and duration come from the job specification and current product instructions.
A planning guide, not a substitute for the specification, product instructions or competent site supervision.
Setting ≠ curing ≠ drying ≠ loading
Setting
The mix stiffens and loses workability. That does not mean it is ready to carry loads.
Curing
Managing moisture and temperature so hydration and strength development can continue.
Drying
Moisture leaving the slab. Floor finishes need the specified moisture checks, not a guessed calendar date.
Loading
Permission for traffic or load comes from the responsible person, the specification and any required evidence.
Keep the inputs with the answer
A record you can take to site.
Save a versioned project file, export a CSV or print an A4 record. Your dimensions, specification reference, revision and assumptions stay with the result. Optional browser storage is a convenience; the exported file is your durable copy.