U·CUniversal ConcreteFloor quantities & site levels
Menu
Fresh concrete beside exposed reinforcement, with a worker standing on the surface

Fresh concrete beside reinforcement

Two concrete and flooring tools · metric

Compound quantities.
Setting-out levels.

Calculate self-levelling compound bags from measured depths and your product rate, or work out site levels and staff readings from a supplied datum.

01 · Start with the figures you have

Three stages.
Two tools to start.

Work from the measurements, approved drawing and product data sheet for your job. The workbench shows the arithmetic and keeps your assumptions with the result. No login needed.

Self-levelling compound calculator

Add rooms and measured depths, or import a complete regular level grid. Use your exact product rate and thickness limits, then work to one shared bag order.

Public beta

Setting-out levels worksheet

Turn a supplied datum and plane into point RLs and staff readings. Record checks with staff and level errors labelled separately.

Public beta

Setting, curing, drying and loading

Four different stages, not one countdown. Keep the prescribed curing method and the decision about loading separate from quantity arithmetic.

Field guide

These are arithmetic tools, not an engineering sign-off. Check the entered measurements and specification before using a record on site.

Worker guiding fresh concrete from a delivery chute into timber formwork
Placing concrete from a delivery chute

02 · See the working

Show the working,
then the order.

A small example for each tool. These figures illustrate the arithmetic; they are not a recommended product or a design for your job.

Self-levelling compound · example project

Ground-floor rooms

Illustrative two-room compound order
ZoneArea × depthNet
Kitchen10 m² × 3 mm42 kg
Hall5 m² × 6 mm42 kg
Netat 1.4 kg/m²/mm84 kg
Order+10% allowance92.4 kg
5

× 22 kg bags, one shared order
110 kg purchased, none in stock. Rounding each room separately would mean 6 bags.

All product values are illustrative inputs. For a real job, enter the current data-sheet rate, bag size, thickness limits and application for the exact product, as named on its data sheet.

Open the calculator

Setting-out levels · example

Peg P1, one supplied plane

HPC = RL(BM) + backsight

Target staff = HPC − target RL

z = z₀ + gx·(x − x₀) + gy·(y − y₀)

Benchmark 100.500 m, backsight 1.250 m and target RL 100.380 m give a target staff reading of 1.370 m.

An observed staff reading of 1.380 m means staff error +10 mm and level error −10 mm. The surface is 10 mm low, not high. Your specification supplies the tolerance.

Build a setting-out sheet

Concrete field guides

Choose the material.
Check the next step.

Four guides to the distinctions behind an order, a pour or a flooring decision. They explain the terms; your project specification still supplies the requirements.

Cement vs concrete

Separate the binder, the complete concrete mix and a formulated self-levelling compound before ordering.

Types of concrete

Read ready-mixed, self-compacting and structural descriptions without treating a name as a recipe.

Workers levelling fresh concrete with a long straightedge
Levelling freshly placed concrete

03 · Pour & finish guide

Before you place
the first load

  1. Datum and measurements

    Fix one datum and note where its level came from. Measure the base you will actually place material onto. Drawing depths are not a floor survey.

  2. Logistics

    Walk the route from delivery to placement. Confirm access, delivery arrangements and the placing plan with the people responsible for the job.

  3. Specified joints

    Work from the joints on the drawing or specification. If that information is missing, resolve it with the designer rather than guessing a spacing.

  4. Prescribed curing

    Have the specified protection ready before placement. Method, start conditions and duration come from the job specification and current product instructions.

Read the placement checklist

A planning guide, not a substitute for the specification, product instructions or competent site supervision.

Setting ≠ curing ≠ drying ≠ loading

Setting

The mix stiffens and loses workability. That does not mean it is ready to carry loads.

Curing

Managing moisture and temperature so hydration and strength development can continue.

Drying

Moisture leaving the slab. Floor finishes need the specified moisture checks, not a guessed calendar date.

Loading

Permission for traffic or load comes from the responsible person, the specification and any required evidence.

Keep the inputs with the answer

A record you can take to site.

Save a versioned project file, export a CSV or print an A4 record. Your dimensions, specification reference, revision and assumptions stay with the result. Optional browser storage is a convenience; the exported file is your durable copy.